Biomass Power/Cogeneration Programme

Biomass Resource AtlasFinancial Incentives Fiscal Incentives 

 

The Biomass power/cogeneration programme is implemented with the main objective of promoting technologies for optimum use of country’s biomass resources for grid and off grid power generation.  Biomass materials  successfully used for power generation include bagasse, rice husk, straw, cotton stalk, coconut shells, soya husk, de-oiled cakes, coffee waste, jute wastes, groundnut shells, saw dust etc.  The technologies being promoted include combustion/ cogeneration and gasification either for power in captive or grid connected modes or for heat applications.

 

Ø      POTENTIAL

The current availability of biomass in India is estimated at about 500 millions metric tones per year.    Studies sponsored by the Ministry has estimated surplus biomass availability at about 120 – 150 million metric tones per annum covering agricultural and forestry residues corresponding to a potential of about 16,000 MW.  This apart, about 5,000 MW additional power could be generated through bagasse based cogeneration in the country’s 550 Sugar mills, if these sugar mills were to adopt technically and economically optimal levels of cogeneration for extracting power from the bagasse produced by them.
 

TECHNOLOGY

 

        Ø      COMBUSTION

        The thermo chemical processes for conversion of biomass to useful products  involve combustion, gasification or pyrolysis. The most commonly used route is combustion. The advantage is that the technology used is similar to that of a thermal plant based on coal, except for the boiler.  The cycle used is the conventional ranking cycle with biomass being burnt in high pressure boiler to generate steam and operating a turbine with generated steam.  The net power cycle efficiencies that can be achieved are about 23-25%. The exhaust of the steam turbine can either be fully condensed to produce power, or used partly or fully for another useful heating activity. The latter mode is called cogeneration. In India, cogeneration route finds application mainly in industries.

     Ø      GASIFICATION

       Instead of combustion, it is possible to convert the biomass into producer gas by gasification (partial combustion). Thermo-chemical gasification involves burning the biomass with insufficient air so that complete combustion doesn’t occur, but a gaseous product is obtained.  The producer gas is a mixture of carbon monoxide and hydrogen.  Gasifiers are classified as updraft or downdraft depending on the direction of flow of the biomass and producer gas.  India has significant experience in atmospheric gasifiers.

  Ø      COGENERATION IN SUGAR MILLS

6 MW Biomass Power project, Andhra Pradesh

        Sugar industry has been traditionally practicing cogeneration by using bagasse as a fuel.  With the advancement in the technology for generation and utilization of steam at high temperature and pressure, sugar industry can  produce electricity and steam for their own requirements.  It can also produce significant surplus electricity for sale to the grid using same quantity of bagasse.  For example, if steam generation temperature/pressure is raised from 400oC/33 bar to 485oC/66 bar, more than 80 KWh of additional electricity can be produced for each ton of cane crushed.  The sale of surplus power generated through optimum cogeneration would help a sugar mill to improve its viability, apart from adding to the power generation capacity of the country.  

Ø      DEPLOYMENT 

The Ministry has been implementing biomass power /co-generation programme since mid nineties.  A total of   167 biomass power and cogeneration projects aggregating to 1252 MW capacity have been installed in the country for feeding power to the grid.  In addition, around 171 biomass power and cogeneration projects aggregating to 1850 MW of electricity are under various stages of implementation.     Cogeneration projects in sugar mills includes 82 projects with installed capacity aggregating to 690 MW.  Another 107 projects are under implementation aggregating to 1280 MW.  States which have taken  leadership position in implementation of cogeneration projects are Andhra Pradesh, Tamil Nadu, Karnataka and Uttar Pradesh, The leading States for biomass power projects are Andhra Pradesh, Karnataka, Chattisgarh, Maharashtra and Tamil Nadu. 

Ø      MANUFACTURING BASE 

Manufacturing capability exists in the country for the equipment/machinery required for setting up Biomass Projects.  Except for some critical control equipment, and high efficiency turbines, most of the equipments can be procured from indigenous sources.

Boilers

  A number of large manufacturers  have established capabilities for manufacturing spreader stoker fired, traveling grate/dumping grate boilers; atmospheric pressure fluidized bed boilers and circulating fluidized bed boilers. 

   Due to recent upsurge of interest in co-generation for surplus power, leading manufacturers are further upgrading their capabilities for high efficiency boilers.

            Steam Turbines

Almost all combinations – condensing, single extraction/double extraction condensing, back pressure, etc. are now being offered in the country with full after sales services guarantees.  The efficiencies of turbines now being offered are comparable to the best in the world.

         Other Equipment

Apart from the main equipment, there is a well established capability and capacity for manufacture of  related equipment for use of biomass for energy including  harvesters, balers, briquetting equipment, handling and firing equipment, pollution control systems , etc.    Many multinational companies have set up manufacturing facilities in the country for such equipment.    

Ø      PROMOTIONAL POLICIES

Besides the Central Financial Assistance, fiscal incentives such as 80% accelerated depreciation, concessional import duty, excise duty, tax holiday for 10 years etc., are available for Biomass power projects. The benefit of concessional custom duty and excise duty exemption  on equipments.  In addition,  State Electricity Regulatory Commissions have determined preferential tariffs and Renewable Purchase Standards (RPS). Indian Renewable Energy Development Agency (IREDA) provides loan for setting up wind power and bagasse cogeneration projects. 

 

Tariff's announced  by the State Electricity Regulatory Commissions

State

Participation

Wheeling

Banking

Buy Back

Third Party Sale

Other Incentives

A.P.** 

 

Pvt.

28.4% + Rs.0.5/kwh

Allowed at 2% for 8-12 months

Rs.2.63 per unit, (05-06) @1%  for  5 years

Not Allowed

--

Chattishgarh **

Pvt.

6%

Not allowed

Rs.2.67  (04-05)  

Rs.2.71 (05-06)

Allowed

As to other industry; Electricity Duty Exempted for 1st  five year

Gujarat**

Pvt.

 4% of energy

 Allowed 12 months

Rs.3.00/unit, 

No escalation   

 Allowed

--

Haryana **

(RPS-3%-07-08)

Pvt.

2% of energy

 Allowed 

BM -Rs.4.00/unit,  BC-3.74/unit

2%  escalation    (base year07-08)

 Allowed

--

Karnataka**

Pvt.

5% surcharge Rs.1.13/unit

Allowed at 2% charge on monthly basis

 Rs.2.74 per unit,  (cogeneration)

@Rs.2.88 per unit(04-05) 1% on base year 10 yrs. (Biomass)

--

 

Subsidy @ Rs.25 lakhs/MW for co-gen. only

Kerala

Pvt.

5% of energy

Allowed 4 months

Rs.2.80 per unit, escalated at  5% for five years (2000-01)

Not allowed

50% cost of power evacuation line to be borne by KSEB.

Maharashtra**

Pvt./Coop.

7% of energy

Allowed

Rs.3.05 per unit (Comm  yr.) (Cogen)

@ Rs.3.04 - 3.43   (13 yrs. ) @1% (biomass)

Allowed

50% cost of power evacuation line to be borne by MSEB.

M.P **

Pvt.

  Yet to be decided

 Allowed

Rs.3.33 to 5.14 paise for 20 yrs. With escl of 3- 8paise

Allowed

--

Punjab

Pvt.

2% of energy

Allowed 12 months

Rs.3.01 per unit, escalated at 3% for 5 years (01-02), Rs.3.48 (maximum)

Allowed

As to other industry

Rajasthan**

Pvt.

10% of energy

Allowed 12 months

Rs.3.60 per unit,  (07-08)-water cooled and Rs.3.96- air cooled 

Allowed

--

Tamil Nadu

Pvt.

2% - 10%

Allowed at 2% charge

Rs.2.73 per unit,*** escalated at 5% for 9 Years (2000-01)

Not Allowed

--

U.P **

Pvt.

12.5%*

Allowed 24 months

 Rs.2.86 per unit, for existing and 2.98 for new with  escalated at  4 paise/year

Allowed*

--

*  Not allowed for Co-generation

**  Policy announced by SERC in respective States.

 Note: For details and upto date information concerned SERCs/State Govts website may be consulted.

 


Pattern of Central Financial Assistance/Incentives for Setting up of Biomass Power / Cogeneration projects

                   Eligibility: 

Biomass Based Project

 

 

 

Biomass Power (combustion)

:

·       Minimum 62 bar steam pressure

·       Maximum of upto 15% use of fossil fuel of total energy consumption in K.cals or as per DPR, whichever is less.

·       For only new boilers and turbines

     (capacity limited to in accordance with the estimated potential in a state)   

Co-generation

:

·       Minimum 40 bar steam pressure

·       Maximum of upto 15% use of fossil fuel of total energy consumption in K. cals.  or as per DPR, whichever is less, during crushing season. 

Biomass power with advanced

technology

 

:

 

 

Capital subsidy for Bagasse/biomass cogeneration projects.

 

 

Special Category States

(NE Region, Sikkim, J&K, HP & Uttaranchal)

Other States

Biomass Based projects

Biomass Power projects

Rs 25 lakh X

(C MW)^0.646

Rs 20 lakh X (C MW)^0.646

Bagasse

Co-generation

Rs 18 lakh X

(C MW)^0.646

Rs 15 lakh X (C MW)^0.646

Bagasse

Co-generation projects by cooperative/ public/joint sector

40 bar & above

60 bar & above

80 bar & above

 

 

 

 

 

 

     Rs. 40 lakh    *

Rs. 50 lakh 

Rs. 60 lakh 

Per MW

(maximum support Rs. 8.0 crore per project)

 

 

 

 

 

      Rs. 40 lakh    *

Rs. 50 lakh 

Rs. 60 lakh 

Per MW

 (maximum support Rs. 8.0 crore per project)

Biomass Power using Advanced Technologies

Rs. 1.2 crore X

(C MW)^0.646

 Rs. 1.0 crore X (C MW)^0.646

 *For new sugar mills (which are yet to start production and sugar mills employing backpressure route/seasonal/incidental cogeneration) subsidies shall be one-half of the level mentioned above.

Fiscal Incentives for Biomass Power Generation

 

Item

Description

Accelerated Depreciation

80% depreciation in the first year can be claimed for the following  equipment required for co-generation systems:

  1. Back pressure, pass-out, controlled extraction, extraction–cum-condensing turbine for co-generation with pressure boilers
  2. Vapour absorption refrigeration systems
  3. Organic rankine cycle power systems   
  4. Low inlet pressures small steam turbines

Income Tax Holiday

Ten years tax holidays.

 

Customs Duty

 Concessional customs and excise duty exemption for machinery and components for initial setting up of projects.

General Sales Tax

Exemption is available in certain States

 

STATE-WISE/YEAR-WISE LIST OF COMMISSIONED BIOMASS POWER /                 CO-GENERATION PROJECTS (AS ON 30.09.2007)
(In MW)
                   
S.No. State upto 31.03.2002 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 Total
1 Andhra Pradesh 101.20 58.85 37.70 69.50 12.00 22.00 33.00 334.25
2 Chattisgarh 11.00 -- -- -- 16.50 85.80 17.50 130.80
3 Gujarat 0.50 -- -- -- -- -- -- 0.50