The Green Energy Corridor Project aims at synchronizing electricity produced
from renewable sources, such as solar and wind, with conventional power
stations in the grid.
For evacuation of large-scale renewable energy, Intra State Transmission
System (InSTS) project was sanctioned by the Ministry in 2015-16. It is being
implemented by eight renewable-rich states of Tamil Nadu, Rajasthan, Karnataka,
Andhra Pradesh, Maharashtra, Gujarat, Himachal Pradesh, and Madhya Pradesh. The
project is being implemented in these states by the respective State
Transmission Utilities (STUs).
The project
includes approximately 9400 ckm transmission lines and substations of a total
capacity of 19000 MVA to be completed by March 2020. The purpose is to evacuate
20,000 MW of large-scale renewable power and improvement of the grid in the
implementing states.
The total project cost is Rs. 10141 crores. The funding mechanism
consists of 40% Government of India Grant (total Rs. 4056.67 crores), 20% state
equity and 40% loan from KfW, Germany (500 million EUR).
The Central grant is disbursed in two installments to the STUs: a) 70%
advance on the award of contract, and b) balance 30% after successful
commissioning and three months of performance testing.
Institutional
Arrangements & Implementation Strategy
The project is being implemented by respective State Transmission Utilities (STUs) allocating the work through a competitive bidding process. The Ministry monitors the project every month. A Project Appraisal Committee under the chairmanship of concerned Joint Secretary and with members from CEA & PGCIL monitors the project & recommends on
the disbursal of the central
grant to the STUs.
Status as on 31 December 2019:
|
Intra-State Transmission System |
||
|
State |
Lines Target (ckm) |
Line constructed (ckm) |
|
Tamil Nadu |
1068 |
906 |
|
Rajasthan |
1054 |
740 |
|
Andhra Pradesh |
1073 |
429 |
|
Himachal Pradesh |
502 |
147 |
|
Gujarat |
1908 |
965 |
|
Karnataka |
618 |
445 |
|
Madhya Pradesh |
2773 |
2186 |
|
Maharashtra |
771 |
358 |
|
Total |
9767 |
6258 |
|
Inter-State Transmission System |
||
|
ISTS Line Details |
Line constructed (ckm) |
Status |
|
Ajmer (New)- Ajmer (RVPN) 400kV D/c |
131 |
Completed |
|
Chittorgarh (New)- Chittorgarh (RVPN) 400kV D/c |
97 |
Completed |
|
Tirunelveli Pooling Station - Tuticorin Pooling
Station 400 kV 2xD/c |
48 |
Completed |
|
Chittorgarh – Ajmer (New) 765kV D/c |
422 |
Completed |
|
Banaskantha
– Chittorgarh 765kV D/c |
604 |
Completed |
|
Banaskantha
– Sankhari (RVPN) 400 kV D/c |
43 |
Completed |
|
Bhuj Pool – Banaskantha
765kV D/c |
578 |
Completed |
|
Ajmer (New)
– Bikaner (New) 765 kV D/c |
526 |
Completed |
|
Bikaner
(New) – Moga(PG) 765 kV D/c - 734 ckm |
601 |
Under
construction |
|
LILO of one
circuit of 400 kV Bhadla – Bikaner (RVPN) line at Bikaner (New) |
18 |
Completed |
|
Total |
3068 |
|