CFA PROVIDED UNDER VARIOUS RENEWABLE ENERGY SCHEMES/ PROGRAMMES

 

I.          Grid-interactive power programme 

 

 

Special Category States      (NE Region, Sikkim, J&K, HP & Uttaranchal)

Other States

Small Hydro Power projects

Rs.2.25 crore X

(C )^0.646

Rs.1.50 crore X

(C )^0.646

Biomass Power projects

Rs.25 lakh X

(C )^0.646

Rs.20 lakh X

(C )^0.646

Bagasse Co-generation

projects by private sector

 

40 bar & above

  

 

Rs.18 lakh X

(C )^0.646

 

 

Rs.15 lakh X

(C )^0.646

Bagasse Co-generation projects by cooperative/ public/joint sector

40 bar & above

60 bar & above

80 bar & above

 

 

 

 

Rs.40 lakh/MW

Rs.50 lakh/MW

Rs.60 lakh/MW

(maximum support              Rs.8.0 crore per project)

 

 

 

 

Rs.40lakh/MW

Rs.50 lakh/MW

Rs.60 lakh/MW

(maximum support

 Rs.8.0 crore per project)

Biomass Power using Advanced Technologies

Rs.1.2 crore X

(C)^0.646

Rs.1.0 crore X

(C )^0.646

Wind Power projects

Rs.3.00 crore X

(C )^0.646

Rs.2.50 crore X

(C)^0.646

                       C - Capacity of the project in MW;                ^: raised to the power

  *    For new sugar mills (which are yet to start production and sugar mills employing backpressure route/seasonal/incidental cogeneration) subsidies shall be one-half of the level mentioned above.

 

II.  Off-grid renewable energy programmes:      

S. No.

Programmes/Sector

Subsidy

1.

Small aero-generators and hybrid systems

75% of ex-works cost or Rs.2.00 lakh/kW, whichever is less, in other areas, for government community use.

 50% of ex-works cost or Rs.1.25 lakh/kW, whichever is less, for all other users

2.

 

Family Type biogas plants

 

NE Region States including Sikkim (except plain areas of Assam)

 

Plain areas of Assam

 

J&K, Himachal Pradesh,                 Uttaranchal (excluding terai region),

Nilgiris of Tamil Nadu,

Sadar Kursoong and Kalimkpong

sub-divisions of Darjeeling, Sunderbans, A&N Islands

 

Scheduled Caste, Scheduled Tribe desert districts, small and marginal farmers, landless laborers, terai region of Uttaranchal, Western Ghats and other notified hilly areas.

All Others

 

 

Rs.11,700 for 1 cum. 

 

 

Rs.9,000 1 cum.

 

Rs.4,500 (limited to Rs.3,500/- for 1 cum. fixed dome type plant)

 

 

 

Rs.3,500  (limited to Rs. 2,800/- for 1 cum. fixed dome type plant)

 

Rs.2,700 (limited to Rs. 2,100/- for 1 cum. fixed dome type plant)

3 (i).

Biomass Gasifiers for rural areas

Rs.1.50 lakh/100 kWe - for thermal and electro-mechanical applications (with dual fuel engine)Rs.15.00 lakh/100 kWe - for power generation upto 1MW (with 100% producer gas engine)

20% higher subsidy for Special Category States & Islands 

(ii)

Biomass gasifier for industrial applications

Rs.2.00 lakh/300 kWe for thermal applications

Rs.2.50 lakh/100 kWe with dual fuel engine

Rs.10.00 lakh/100 kWe with 100% producer gas engine

Rs.15.00 lakh/100 kWe with 100% producer gas engine in institutions

4.

Industrial Waste-to-Energy projects

 

Rs.50.00 lakh to Rs.1.00 crore/ MWe, depending on technology.

(20% higher subsidy for Special Category States)

5.

Solar Photovoltaic (SPV)

SPV lanterns

 

SPV home lighting systems.

 

 

 

SPV street lighting systems

 

SPV standalone power plant of capacity  > 1 kWp

 

SPV standalone power plant of capacity  > 10 kWp

 

Rs.2,400 for NE and special areas; nil for other

 

Rs.4500 to 8,600 for NE and special areas, and

Rs.2500 to 4,800 for general areas, depending on model

 

Rs.17,300 for NE and special areas

Rs.9,600 for general areas

 

Rs.2,25,000/kWp for NE and special areas

Rs.1,25,00/kWp for general areas

 

Rs.2,70,000/kWp  for NE and special areas

Rs.1,50,000/kWp for general areas

6.

Solar Photovoltaic (SPV) applications in Urban Areas:
 

SPV streetlight control systems

 

SPV street/public garden lights         

 (74/75 Wp modules)

 

SPV illuminated  hoardings

(with maximum 1kWp SPV module)

 

SPV road studs

 

SPV blinkers

(minimum 37 Wp module)

 

SPV traffic signals

 (minimum  500 Wp module)

 

SPV power packs

(maximum 1 kWp module)

 

 

 

25% of cost subject to a max. of Rs. 5000/-

 

50% of cost subject to a max. of Rs.10,000/- &  Rs.12,000/- for 11 W and 18 W CFL respectively

 

50% cost subject to a max. of Rs.15,000/100 Wp module

 

50% of cost subject to a maximum Rs. 1000/-

 

 

50% of cost subject to a maximum Rs. 7,500/-

 

50% of cost subject to a maximum Rs.2.5 lakh

 

 

50% of cost subject to a maximum Rs. 1.00 lakh per kWp

7.

SPV water pumping systems

Rs.30/Wp of SPV array used, subject to a maximum of Rs.50,000 per system.

8.

Solar Thermal systems/ devices

 

Box type cookers:

Incentive to SNA:

- Rs.200 per cooker of ISI brand

-  Rs.100 per cooker of non-ISI brand

- Upto Rs.1.50lakh for publicity / workshops etc.

-  support to manufacturers : reimbursement of  50% fees for obtaining BIS approval.

 

Solar Water Heating systems:  

-Subsidized Loan @ 2% to domestic users, 3% to institutions and 5% to community users plus Rs.100/square meter of collector area as incentive to motivator.

 

-Capital subsidy @ Rs. 825/1100 per sqm. to commercial establishments/ institutions

 

Solar Air Heating/ Steam Generating Systems:

Capital subsidy @ 35-50% of the cost subject to certain ceilings.

 

Dish / community type solar cookers:

50% of cost limited to Rs.2,500 for dish type cookers and Rs.25,000 for Scheffler/community type cooker.

9.

Akshay Urja Shops

Subsidized loan @7% upto Rs.10 lakh and performance based grant & incentive up to Rs.10,000 per month.

III. Remote Village Electrification Programme:          

1.

 

 

Remote Village Electrification

90% of the costs of electricity generation systems subject to pre-specified maximum and the following ceilings:

- Rs.18,000 per household for distributed generation systems, and

-     Rs.11,250 per household for SPV home-lighting systems.